Whanganui Wharf One Upgrade

LOCATION Whanganui    PRINCIPAL Whanganui   PROJECT DATES February 2016 to November 2016

Design and refurbishment of a 100m long wharf. Works included construction timber pile repairs, timber bent replacement and refurbishment, sheetpiling, tiebeams & deadmen, engineered fill, insitu concrete suspended deck and concrete pavement. Works also included demolition of 50m of the existing wharf.

Quality/Achievement: A CSL Project Quality Plan was produced and followed in accordance with our AS/NZS ISO9001 certification. There were no significant defects of remedial works required. The contract was a design and build and CSL exceeded the clients expectation by providing a bridge which required no works to be carried out in the waterway.

Time Management: The overall project was completed 3 weeks ahead of the due date.

Health & Safety: Health and Safety Plan implemented and observed in accordance with the company’s secondary level
requirements for ACC WSMP. There were zero LTIs.

Environmental: CSL was committed to providing comprehensive Environmental Management throughout the project, with protection of the Whangaheu River always the highest concern. There were no environmental incidents on this project.

Traffic Management: A specific traffic management plan was produced to control the movement of site traffic and machinery for this project.

Public Relations & Cooperative team approach: CSL had a good rapport with the Main Contractor, associated subcontractors and stakeholders. Work was well planned to minimize the impact on other operations within the site.

Management/Administration: All aspects of management requirements were met including reporting, communications, financial control and risk management.