21 Jan Central Transport Limited
LOCATION Central Transport Limited, Broadlands Rd, Reporoa • PRINCIPAL Lugerburn Trust • PROJECT DATES May 2012 to September 2012
Design and Construction of a 900m² Workshop and 300m² Office and Staff Facilities. Works included all Foundation Works, Manufacture and Erection of Precast Panels, Footpaths and Carpark Area.
Quality: The project Quality Management Plan was implemented and observed in accordance with our AS/NZS ISO9001 certification. No remedial works were required on the project.
Health & Safety: There were no issues with Health and Safety on this site. No accidents or near misses were recorded.
Environmental: The environmental risks were minimal and no major environmental damage or loss was recorded.
Traffic Management: No traffic management was required as it was on private land and deemed a construction site with restricted access.