Design and Construction of a circular prestressed, post tensioned 9m high, 30m diameter water retaining structure, including all associated pipe work, safety ladders, site drainage and sundry works.  The project was completed within the anticipated contract period of 40 weeks and within the contract budget....

Design and construction of two 100m long x 3 span bridges over the Mangawhero River, 250,000m³ of earthworks including 60,000m³ of rock excavation. Works also included the design and build of two reinforced earth retaining walls up to 12m high, 1.6km of pavement and associated...

The construction of a 20 x 18 x 7m deep in-ground concrete structure for a pump station. The scope included the installation and extraction of a sheet pile cofferdam, a 7m deep wet excavation into a live aquifer, 2m thick tremie poured concrete plug, insitu...

This project involved the manufacture of piles adjacent to an existing and fully operational wharf. The project was completed on time, under budget, encountered no problems with health and safety and met the environmental and consent conditions imposed....

The Waimakariri R501 Bridge had been undermined through scouring of the riverbed to such an extent that during the flood periods the bridge had to be closed to all traffic. The project required the strengthening of six piers to allow the bridge to remain open...

The Whakapapa Intake forms part of the Turangi Power Scheme and was constructed in the 1960’s. Over the years, the stilling basin apron suffered hydraulic erosion to the concrete. The works required the dewatering of the river and the construction of a 300m3 concrete overlay....