11 Jun Bulls Reservoir
LOCATION Bulls Reservoir, Bulls • PRINCIPAL Rangitīkei District Council • PROJECT DATES September 2012 to October 2012
Design and Construction of a new 1300m3 water reservoir in Bulls, along with seismic strengthening of the existing Bulls mushroom shaped water tower.
Programme: The construction work was completed within the expected 4.5 month programme period, completion occurring 25 May 2021.
Quality: Project Quality was implemented and observed in accordance with the company’s AS/NZS ISO 9001:2015 Certification. There were no non-conformances recorded and no remedial works required.
Health & Safety: A site specific Health and Safety Management Plan was implemented and observed. No workplace accidents occurred.